10.06.2018

KAHRAMAA commissioned Al-Wa'ab electricity substation, the third for Doha metro

1

Qatar General Electricity and Water Corporation “KAHRAMAA” successfully commissioned Al-Wa'ab City Metro substation, the third Doha Metro electricity substation that KAHRAMAA implements for Qatar Rail.

On this occasion, KAHRAMAA President H.E. Eng. Essa bin Hilal Al-Kuwari said "As the Corporation is a key partner in the development projects that the State is witnessing, we are proud to supply power to Doha Metro project “  

KAHRAMAA President explained that Doha Metro substations were given priority in awarding projects, it is one of KAHRAMAA challenges which was successfully implemented with the highest quality standards. All technical requirements pertinent to the use of technology that ensures the continuity of electrical energy in emergency cases were adopted.

He also added: "one year has passed on the unjust blockade imposed on Qatar and yet we are celebrating today the completion of the third substation out of five electricity substation that are implemented by KAHRAMAA for Qatar Rail " emphasizing that the Corporation can expand the service if needed in the future”

He concluded by saying “we reiterate our commitment to complete all infrastructure projects on time in conformity with the instructions of His Highness Sheikh Tamim Bin Hamad Al Thani, Amir of the State Qatar and with the full support of our wise government.”

Al Waab City Metro 132/33 KV substation located in Al Waab area, is part of the 12th phase of the Qatar Power Transmission System Expansion project. It was awarded in 2016 and is fed by Al Waab Super Substation with 1.3 km long and 132 Kv cable. The project total cost is around QR 100 million.

KAHRAMAA in cooperation with Qatar Rail is working to provide the highest standards of reliability and consistency in its electrical network in conformity with the highest international standards and according to the Metro requirements

Additionally, KAHRAMAA’s main concern is to adopt and implement the highest standards of safety and security in its activities and operations. Hence, all along the 30 months of work on the project, with more than 816,000 work hours completed at Al Waab City Metro substation without Lost Time Injury (LTI). As well, the Corporation is committed to providing the highest standards of welfare and living conditions to its staff in recognition of their role as partners in success, which positively affect productivity

 

KAHRAMAA is implementing five substations for Qatar Rail to supply Doha Metro with all its electricity needs at a total cost of about 700 million Qatari Riyals. Ras Abu Fontas the first substation was commissioned in July 2017 followed by Lusail substation in March 2018. The next substation will soon be commissioned in west of Doha in addition to Al Bidaa substation, which will include parking facilities. It is expected to be commissioned in the second half of 2019

Quick Access
Quick Access
Our use of Cookies
We understand that your online privacy is very important, and we want to put you in control of your data.
You have the option to decline cookies that we automatically place on your browser; however, allowing Kahramaa and our trusted partners to use cookies or similar technologies will give you a truly remarkable browsing experience and help us improve our content and communication with you.
We will not set optional cookies unless you enable them, and you can change your cookie preferences at any time by using the tool. For more information, please read our Privacy policy.